Civil Construction Progress of April 2008

Line: 13 to 13
 
META FILEATTACHMENT attachment="image002.jpg" attr="" comment="The entrance portal" date="1240399796" name="image002.jpg" path="image002.jpg" size="30458" stream="image002.jpg" tmpFilename="" user="wangm" version="1"
META FILEATTACHMENT attachment="image008.jpg" attr="" comment="The construction tunnel" date="1240399842" name="image008.jpg" path="image008.jpg" size="24034" stream="image008.jpg" tmpFilename="" user="wangm" version="1"
Added:
>
>
META TOPICMOVED by="wangm" date="1240469833" from="Public.CivilProgress200804" to="Public.CivilProgressBefore"

 <<O>>  Difference Topic CivilProgressBefore (3 - 2009-04-23 - WangMeng)
Line: 1 to 1
 
META TOPICPARENT name="ProjectProgress"

Civil Construction Progress of April 2008

  • Finished the backfill on the top of entrance tunnel.
  • Construction tunnel excavation 53.2 m, total finish 77.5 m.
  • Finished 152 m depth of 26 SAB base pickets construction, total finish 160 m depth which is 51.9% of the total work.
Deleted:
<
<
  • Due to the Apr. 4 accident, the blast work are suspended.
  | The entrance portal The entrance portal

 <<O>>  Difference Topic CivilProgressBefore (2 - 2009-04-22 - WangMeng)
Line: 1 to 1
 
META TOPICPARENT name="ProjectProgress"

Civil Construction Progress of April 2008

Added:
>
>
  • Finished the backfill on the top of entrance tunnel.
  • Construction tunnel excavation 53.2 m, total finish 77.5 m.
  • Finished 152 m depth of 26 SAB base pickets construction, total finish 160 m depth which is 51.9% of the total work.
  • Due to the Apr. 4 accident, the blast work are suspended.
 
Changed:
<
<
| |
>
>
| The entrance portal The entrance portal | The construction tunnel The construction tunnel
 | \ No newline at end of file
Added:
>
>
META FILEATTACHMENT attachment="image002.jpg" attr="" comment="The entrance portal" date="1240399796" name="image002.jpg" path="image002.jpg" size="30458" stream="image002.jpg" tmpFilename="" user="wangm" version="1"
META FILEATTACHMENT attachment="image008.jpg" attr="" comment="The construction tunnel" date="1240399842" name="image008.jpg" path="image008.jpg" size="24034" stream="image008.jpg" tmpFilename="" user="wangm" version="1"

 <<O>>  Difference Topic CivilProgressBefore (1 - 2009-04-22 - WangMeng)
Line: 1 to 1
Added:
>
>
META TOPICPARENT name="ProjectProgress"

Civil Construction Progress of April 2008


View | History: r4 < r3 < r2 < r1 | More

View | History: r4 < r3 < r2 < r1 | More
This site is powered by the TWiki collaboration platform Powered by Perl Powered by the TWiki collaboration platform Copyright © by the contributing authors, 2007-2026.
Ideas, requests, problems regarding Daya Bay? Send feedback