Civil Construction Progress of April 2008

  • Finished the backfill on the top of entrance tunnel.
  • Construction tunnel excavation 53.2 m, total finish 77.5 m.
  • Finished 152 m depth of 26 SAB base pickets construction, total finish 160 m depth which is 51.9% of the total work.
  • Due to the Apr. 4 accident, the blast work are suspended.

The entrance portal The entrance portal The construction tunnel The construction tunnel
I Attachment History Action Size Date Who Comment
JPEGjpg image002.jpg r1 manage 29.7 K 2009-04-22 - 19:29 WangMeng The entrance portal
JPEGjpg image008.jpg r1 manage 23.5 K 2009-04-22 - 19:30 WangMeng The construction tunnel
Edit | Attach | Watch | Print version | History: r4 < r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...

This site is powered by the TWiki collaboration platform Powered by Perl Powered by the TWiki collaboration platform Copyright © by the contributing authors, 2007-2026.
Ideas, requests, problems regarding Daya Bay? Send feedback