Civil Construction Progress of April 2008

  • Finished the backfill on the top of entrance tunnel.
  • Construction tunnel excavation 53.2 m, total finish 77.5 m.
  • Finished 152 m depth of 26 SAB base pickets construction, total finish 160 m depth which is 51.9% of the total work.
Deleted:
<
<
  • Due to the Apr. 4 accident, the blast work are suspended.
  | The entrance portal The entrance portal