Civil Construction Progress of April 2008
- Finished the backfill on the top of entrance tunnel.
- Construction tunnel excavation 53.2 m, total finish 77.5 m.
- Finished 152 m depth of 26 SAB base pickets construction, total finish 160 m depth which is 51.9% of the total work.
|
|
< < |
- Due to the Apr. 4 accident, the blast work are suspended.
|
| |
| The entrance portal |