Civil Progress of February 16 - March 15, 2009
Milestones
Feb. 18: started the excavation of main tunnel #3.
Feb. 23: started the excavation of water-pit hall.
Feb. 26: started the excavation of Hall-4
Mar. 8: finished the concrete pouring of SAB.
Mar. 12: the 1st AD SSV transported to SAB.
» more
Mar. 14: finished the excavation of the dome of Hall-1.
Mar. 15: finished the concrete lining of access tunnel.
Pictures
Lining the access tunnel
The 1st SSV arrived in SAB.