Civil Progress of February 16 - March 15, 2009
Milestones
- Feb. 18: started the excavation of main tunnel #3.
- Feb. 23: started the excavation of water-pit hall.
- Feb. 26: started the excavation of Hall-4
- Mar. 8: finished the concrete pouring of SAB.
- Mar. 12: the 1st AD SSV transported to SAB. » more
- Mar. 14: finished the excavation of the dome of Hall-1.
- Mar. 15: finished the concrete lining of access tunnel.
Pictures
|
|
| Lining the access tunnel |
The 1st SSV arrived in SAB. |
|
|
| Road construction near the SAB |
Concrete work for pump room and water tank. |