Daya Bay Reactor Neutrino Experiment
Public > CivilConstruction > CivilProgress200903 (r2)
Daya Bay webs: Public | 中文 | Internal | Help   Log In or Register

Users | Groups | Changes | Index | Search | Go

Civil Progress of February 16 - March 15, 2009

Milestones

  • Feb. 18: started the excavation of main tunnel #3.
  • Feb. 23: started the excavation of water-pit hall.
  • Feb. 26: started the excavation of Hall-4
  • Mar. 8: finished the concrete pouring of SAB.
  • Mar. 12: the 1st AD SSV transported to SAB. » more
  • Mar. 14: finished the excavation of the dome of Hall-1.
  • Mar. 15: finished the concrete lining of access tunnel.

Pictures

image004.jpg image006.jpg
Lining the access tunnel The 1st SSV arrived in SAB.
image008.jpg image010.jpg
Road construction near the SAB Concrete work for pump room and water tank.
Edit | Attach | Watch | Print version | History: r4 < r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...

This site is powered by the TWiki collaboration platform Powered by Perl Powered by the TWiki collaboration platform Copyright © by the contributing authors, 2007-2026.
Ideas, requests, problems regarding Daya Bay? Send feedback