Civil Construction Progress of April 2008 Finished the backfill on the top of entrance tunnel. Construction tunnel excavation 53.2 m, total finish 77.5 m...
Civil Progress of February 16 March 15, 2009 Milestones Feb. 18: started the excavation of main tunnel #3. Feb. 23: started the excavation of water pit...