---+!! Civil Progress of February 16 - March 15, 2009 ---++ Milestones * Feb. 18: started the excavation of main tunnel #3. * Feb. 23: started the excavation of water-pit hall. * Feb. 26: started the excavation of Hall-4 * Mar. 8: finished the concrete pouring of SAB. * Mar. 12: the 1st AD SSV transported to SAB. [[CivilProgress20090312][» more]] * Mar. 14: finished the excavation of the dome of Hall-1. * Mar. 15: finished the concrete lining of access tunnel. ---++ Pictures %TABLE{columnwidths="50%,50%" dataalign="center"}% | <img src="%ATTACHURLPATH%/image004.jpg" alt="image004.jpg" width='100%' /> \ | <img src="%ATTACHURLPATH%/image006.jpg" alt="image006.jpg" width='100%' /> \ | | Lining the access tunnel \ | The 1st SSV arrived in SAB. \ |